| 06/07/2026 | 10/07/2026 | Summary of site works planned on the following Elevations, Courtyard and Overall -
week commencing 6th July:
E1-E2-E3-E5:
Scaffold strike on hold whilst cleaning options to remove stubborn embedded stains that have remained following the doff clean are considered.
E3-E4-E5-E6-E7-E8:
Masonry wall survey for remediation works
E11:
Reinstatement of balcony glass, snagging and final clean down to Flats 27, 40, 53, 66 & 79
E11:
Removal of scaffold, hoist and haki staircase
Courtyard:
Refurbishment to parapet walls within garden area.
Overall :
Removal of waste materials from site and various smaller tasks, including outstanding mastic application.
To date:
The original cladding works are approximately 99% complete.
Original contracted cladding works are complete on Elevations: E1, E2, E3, E4 and E5.
Original additional works scope complete on Elevations: E4, E5, E6, E7, E8.
E1 and E2 additional works completed ahead of schedule.
E1 and E2 external doff cleaning of the brickwork to remove efflorescence, soiling and staining completed ahead of programme.
E12 & E13 scaffold strike completed.
Installation of the structural steels to support the deflected balconies completed.
E11 K System cladding installation completed.
Further updates for the remaining weeks:
All original contracted cladding works to be 100% complete.
Scaffold strike to be completed.
E11 Reinstatement of balcony decking upon new support system to be completed.
E11 Balustrade redecoration to be completed.
E1 & E2 scaffold strike to be completed following final clean down.
E11 Scaffold/hoist/Haki staircase removal to be completed.
All Doff cleaning to date to be signed off.
E3, E4, E5, E6, E7 & E8 Masonry wall survey for remediation works to be completed.
E11 Installation of insulated render system and reinstatement of balcony decking to Flats 27, 40, 53, 66 & 79 to be completed.
E11 Remaining materials to be removed, final clean down, snagging and scaffold strike to be completed over the next few weeks.
Ground floor openings (cavities around main entrance, bin stores, and electrical rooms) to be closed.
Ground level redecoration including gates (additional works).
Courtyard - removal of cutting compound equipment and final tidy up following reinstatement of balcony decking to E11 to be completed.
Courtyard pathways to be cleaned.
Courtyard planters to be cleaned, repaired and repainted.
Existing ramp EPS to be painted.
Wall rebuild and render, following ramp removal.
E3 terrace decks and redecoration pending formal instruction.
External doff cleaning of remaining brickwork and scaffold strike on hold pending formal instruction on scope of remediation to brickwork elevations.
| Yes |
| 29/06/2026 | 03/07/2026 | Summary of site works planned on the following Elevations, Courtyard and Overall -
week commencing 29th June:
E3, E4, E5, E6, E7 & E8:
Masonry wall survey for remediation works
E11:
Reinstatement of balcony decking and painting of ballustrades to Flats 27, 40, 53, 66 & 79.
Courtyard:
Removal of equipment and materials from cutting area and general clean up ongoing. Cutting station and compound to remain until balcony decking reinstatement is complete.
Courtyard:
Refurbishment to parapet walls within garden area.
Overall :
Removal of waste materials from site and various smaller tasks, including outstanding mastic application, to be undertaken.
To date:
The original cladding works are approximately 99% complete.
Original contracted cladding works are complete on Elevations: E1, E2, E3, E4 and E5.
Original additional works scope complete on Elevations: E4, E5, E6, E7, E8.
E1 and E2 additional works completed ahead of schedule.
E1 and E2 external doff cleaning of the brickwork to remove efflorescence, soiling and staining completed ahead of programme.
E12 & E13 scaffold strike completed.
Installation of the structural steels to support the deflected balconies completed.
E11 K System cladding installation completed.
Further updates for the remaining weeks:
All original contracted cladding works to be 100% complete.
Scaffold strike to be completed.
E11 Reinstatement of balcony decking upon new support system to be completed.
E11 Balustrade redecoration to be completed.
E1 & E2 scaffold strike to be completed.
E11 Scaffold/hoist/Haki staircase removal to be completed.
All Doff cleaning to date to be signed off.
E3, E4, E5, E6, E7 & E8 Masonry wall survey for remediation works to be completed.
E11 Installation of insulated render system and reinstatement of balcony decking to Flats 27, 40, 53, 66 & 79 to be completed.
E11 Remaining materials to be removed, final clean down, snagging and scaffold strike to be completed over the next few weeks.
Ground floor openings (cavities around main entrance, bin stores, and electrical rooms) to be closed.
Ground level redecoration including gates (additional works).
Courtyard - removal of cutting compound equipment and final tidy up following reinstatement of balcony decking to E11 to be completed.
Courtyard pathways to be cleaned.
Courtyard planters to be cleaned, repaired and repainted.
Existing ramp EPS to be painted.
Wall rebuild and render, following ramp removal.
E3 terrace decks and redecoration pending formal instruction.
External doff cleaning of remaining brickwork and scaffold strike on hold pending formal instruction on scope of remediation to brickwork elevations.
| Yes |
| 12/11/2025 | | *** Safety Reminder to Residents ***
Balconies are NOT accessible while scaffolding is up!
Scaffolding is NOT to be used by the residents, nor their visitors for access to other flats or to the roof!
NO Smoking! Cigarette butts must NOT be thrown out of resident’s window or balcony doors onto/near/around the scaffolding!
We appreciate your cooperation and understanding as we work to carry out these essential remediation works.