Project ReferenceStart DateEnd DateInformationActive
SHS23/11/202626/03/2027Courtyard worksYes
SHS09/11/202604/12/2026Summary of Works expected over the month of November: - Elevations E1-E3: Continue the installation of galvanised steel angles around the window openings to provide fixing points for the new Y-wall backerboard, galvanised angles and plates below the openings and to close off the existing upstand, and the new Y-wall backerboard to the timber studwork and galvanised angles. This element of the works is ongoing and is anticipated to be completed by 13.11.26. - The following week will be dedicated to weatherproofing the backerboard. This will involve sealing all joints with Nullifire, sealing the openings and existing upstand with Obex membrane, and installing Obex breather membrane across the full backerboard area. This element of the works is anticipated to be completed by 20.11.26. - Subject to all necessary design approvals being in place, installation of the rainscreen system can then commence, including brackets, rails, firestopping, insulation and Benx weatherboard cladding. - Site security and compliance checks to be conducted weekly and recorded. - General housekeeping and regular site checks to be conducted. Yes
SHS12/10/202629/01/2027Terrace worksYes
SHS05/10/202606/11/2026Summary of Works carried out during October: - Scaffold build on Elevations E4, E4a, E5 & E6 has been completed and signed over to the site team, including the installation of temporary sheet metal roofing around terrace elevations E1, E2 & E3. - Updated design package has been submitted to the Client/Project Team for review and regulatory approval. - Works at 4th floor terrace level (E1-E3) have included the removal and disposal of the existing weatherboard cladding, battens and Celotex insulation, followed by the cutting and removal of the ply backerboard. - The timber studwork has subsequently been filled with insulation. At the compartment lines, the steelwork has been filled with dense mineral wool and overboarded with Y-wall cement particle board, with PFC firestopping mounted to the board. - Galvanised angles have been installed around the window openings to provide fixing points for the new Y-wall backerboard. Additional galvanised steel angles and plates have been fixed below the openings and to close off the existing upstand. The new Y-wall backerboard has then been installed to the timber studwork and galvanised steel angles. - Site security and compliance checks have been conducted weekly and recorded. - General housekeeping and regular site checks have been conducted. Yes
SHS02/10/202630/10/2026Summary of Works expected over the month of October: - Scaffold build on Elevations E4, E4a, E5 & E6 to be completed and signed over to the site team. - Design package to be submitted to the project yeam for review and regulatory approval. - Material schedule to be finalised and procurement to commence, following approval of design package. - Osprey to conduct phased approach to existing cladding removal, with works to commence on the terrace levels of Elevations E1, E2 & E3. - General housekeeping and regular site checks to be conducted. Yes
SHS30/09/2026Summary of Works carried out to date: - Site accommodation and welfare setup in Flat 1. - Site compound, materials storage area and perimeter security fencing in place on Anning Street. - All external openings for scaffold ties have been completed by Osprey operatives to enable the scaffold build to commence. - Scaffolding complete on Elevation E1, E2 & E3. - Scaffolding on Elevations E4, E4a, E5 and E6 are in progress. - Osprey's Design Team have completed external wall surveys at terrace level to review additional design details. - Electrical Cabling Inspection conducted. - Privacy film has been installed to affected windows, as requested by the residents. - Site security and compliance checks have been conducted weekly. Yes
SHS28/09/202602/10/2026Building Control plans check and Engineers' reviewsYes
SHS31/08/202618/09/2026Osprey's Design Team completing external wall surveys at terrace level to review additional design details.Yes
SHS27/08/2026***SAFETY AND SECURITY NOTICE TO RESIDENTS*** - Scaffold is NOT to be used by residents, nor their visitors, for access to other flats or to the roof! - NO SMOKING! Cigarette butts must NOT be thrown from residents windows or doors onto/near/around the scaffolding! - Terraces are NOT accessible while scaffolding is up! - Windows will only be openable durng out of hours.Yes
SHS26/08/202607/09/2026Scaffold build start on Anning Street - access provision to terraces.Yes
SHS26/08/202604/09/2026Internal Condition Surveys - flats affected will be the ones with timber on the external wall, and the scaffolded rear elevation.Yes
SHS07/08/2026The webpage is now live, project updates will be shared on this page. Yes