| SHS | 26/10/2026 | 05/02/2027 | Courtyard works - proposed to start | Yes |
| SHS | 12/10/2026 | 13/01/2027 | Terrace works – proposed start date postponed to week commencing 12th October | Yes |
| SHS | 05/10/2026 | 30/10/2026 | Summary of Works expected over the month:
- Scaffold build on Elevations E4, E4a, E5 & E6 to be completed and signed over to the site team.
- Design package to be submitted to the project yeam for review and regulatory approval.
- Material schedule to be finalised and procurement to commence, following approval of design package.
- Osprey to conduct phased approach to existing cladding removal, with works to commence on the terrace levels of Elevations E1, E2 & E3.
- General housekeeping and regular site checks to be conducted.
| Yes |
| SHS | 30/09/2026 | | Summary of Works carried out to date:
- Site accommodation and welfare setup in Flat 1.
- Site compound, materials storage area and perimeter security fencing in place on Anning Street.
- All external openings for scaffold ties have been completed by Osprey operatives to enable the scaffold build to commence.
- Scaffolding complete on Elevation E1, E2 & E3.
- Scaffolding on Elevations E4, E4a, E5 and E6 are in progress.
- Osprey's Design Team have completed external wall surveys at terrace level to review additional design details.
- Electrical Cabling Inspection conducted.
- Privacy film has been installed to affected windows, as requested by the residents.
- Site security and compliance checks have been conducted weekly.
| Yes |
| SHS | 28/09/2026 | 02/10/2026 | Building Control plans check and Engineers' reviews | Yes |
| SHS | 31/08/2026 | 18/09/2026 | Osprey's Design Team completing external wall surveys at terrace level to review additional design details. | Yes |
| SHS | 27/08/2026 | | ***SAFETY AND SECURITY NOTICE TO RESIDENTS***
- Scaffold is NOT to be used by residents, nor their visitors, for access to other flats or to the roof!
- NO SMOKING! Cigarette butts must NOT be thrown from residents windows or doors onto/near/around the scaffolding!
- Terraces are NOT accessible while scaffolding is up!
- Windows will only be openable durng out of hours. | Yes |
| SHS | 26/08/2026 | 07/09/2026 | Scaffold build start on Anning Street - access provision to terraces. | Yes |
| SHS | 26/08/2026 | 04/09/2026 | Internal Condition Surveys - flats affected will be the ones with timber on the external wall, and the scaffolded rear elevation. | Yes |
| SHS | 07/08/2026 | | The webpage is now live, project updates will be shared on this page. | Yes |