Project ReferenceStart DateEnd DateInformationActive
SHS26/10/202605/02/2027Courtyard works - proposed to startYes
SHS12/10/202613/01/2027Terrace works – proposed start date postponed to week commencing 12th OctoberYes
SHS05/10/202630/10/2026Summary of Works expected over the month: - Scaffold build on Elevations E4, E4a, E5 & E6 to be completed and signed over to the site team. - Design package to be submitted to the project yeam for review and regulatory approval. - Material schedule to be finalised and procurement to commence, following approval of design package. - Osprey to conduct phased approach to existing cladding removal, with works to commence on the terrace levels of Elevations E1, E2 & E3. - General housekeeping and regular site checks to be conducted. Yes
SHS30/09/2026Summary of Works carried out to date: - Site accommodation and welfare setup in Flat 1. - Site compound, materials storage area and perimeter security fencing in place on Anning Street. - All external openings for scaffold ties have been completed by Osprey operatives to enable the scaffold build to commence. - Scaffolding complete on Elevation E1, E2 & E3. - Scaffolding on Elevations E4, E4a, E5 and E6 are in progress. - Osprey's Design Team have completed external wall surveys at terrace level to review additional design details. - Electrical Cabling Inspection conducted. - Privacy film has been installed to affected windows, as requested by the residents. - Site security and compliance checks have been conducted weekly. Yes
SHS28/09/202602/10/2026Building Control plans check and Engineers' reviewsYes
SHS31/08/202618/09/2026Osprey's Design Team completing external wall surveys at terrace level to review additional design details.Yes
SHS27/08/2026***SAFETY AND SECURITY NOTICE TO RESIDENTS*** - Scaffold is NOT to be used by residents, nor their visitors, for access to other flats or to the roof! - NO SMOKING! Cigarette butts must NOT be thrown from residents windows or doors onto/near/around the scaffolding! - Terraces are NOT accessible while scaffolding is up! - Windows will only be openable durng out of hours.Yes
SHS26/08/202607/09/2026Scaffold build start on Anning Street - access provision to terraces.Yes
SHS26/08/202604/09/2026Internal Condition Surveys - flats affected will be the ones with timber on the external wall, and the scaffolded rear elevation.Yes
SHS07/08/2026The webpage is now live, project updates will be shared on this page. Yes