Work Area TitleTaskStart Date InputEnd Date Input
All Areas
All AreasSite setup22/04/202505/05/2025
All AreasSite clearance and making good06/03/202617/03/2026
Courtyard Elevations
Courtyard ElevationsE9/10 scaffold up and E11 hoist 105/05/202526/05/2025
Courtyard ElevationsE11 scaffold up26/05/202516/06/2025
Courtyard ElevationsE12 scaffold up and hoist 2 (move after backer board fitted)17/07/202530/07/2025
Courtyard ElevationsE9/10 scaffold down11/08/202520/08/2025
Courtyard ElevationsE13 scaffold up (hoist 3 up 06/10/25)14/08/202503/09/2025
Courtyard ElevationsE11 scaffold down23/10/202507/11/2025
Courtyard ElevationsE12 scaffold down08/12/202515/12/2025
Courtyard ElevationsE13 scaffold down10/02/202605/03/2026
External Elevations
External ElevationsE4 scaffold up26/05/202509/06/2025
External ElevationsE5 scaffold up17/06/202508/07/2025
External ElevationsE3 Independent towers up21/07/202525/07/2025
External ElevationsE1 & E2 Independent towers up18/08/202521/08/2025
External ElevationsE4 scaffold down20/10/202527/10/2025
External ElevationsE5 scaffold down10/02/202619/02/2026