A/B Undercroft | | | |
A/B Undercroft | A/B - Complete | 25/11/2024 | 13/01/2025 |
Work Area (B) | | | |
Work Area (B) | B - Complete | 08/04/2024 | 22/08/2024 |
Work Area (D) | | | |
Work Area (D) | D - Complete | 24/06/2024 | 13/02/2025 |
Work Area A | | | |
Work Area A | A - Complete | 11/03/2024 | 22/08/2024 |
Work Area C | | | |
Work Area C | C - Complete | 22/04/2024 | 18/10/2024 |
Work Area E | | | |
Work Area E | E - Complete | 15/07/2024 | 13/02/2025 |
Work Area F | | | |
Work Area F | F front - Scaffold assembly | 28/10/2024 | 08/11/2024 |
Work Area F | F front - Removal and weathering | 02/12/2024 | 23/01/2025 |
Work Area F | F front - Timber cladding replacement | 06/01/2025 | 25/04/2025 |
Work Area F | F front - Replacement | 12/02/2025 | 01/04/2025 |
Work Area F | F front (partial) - Scaffold dismantle | 22/03/2025 | 02/04/2025 |
Work Area F | F front (remaining) - Scaffold dismantle | 12/05/2025 | 30/05/2025 |
Work Area F - Rear | | | |
Work Area F - Rear | F rear - Removal and weathering | 24/01/2025 | 06/03/2025 |
Work Area F - Rear | F rear - Timber cladding replacement | 07/03/2025 | 15/04/2025 |
Work Area F - Rear | F rear - Scaffold assembly | 03/12/2024 | 20/12/2024 |
Work Area F - Rear | F rear - Replacement | 02/04/2025 | 13/05/2025 |
Work Area F - Rear | F rear/front (remaining) - Scaffold dismantle | 12/05/2025 | 30/05/2025 |
Work Area G | | | |
Work Area G | G side - Scaffold assembly | 10/01/2025 | 21/02/2025 |
Work Area G | G side - Removal and weathering | 24/02/2025 | 28/03/2025 |
Work Area G | G side - Replacement | 20/05/2025 | 30/06/2025 |
Work Area G | G side - Remediation | 29/04/2025 | 19/05/2025 |
Work Area G | G front - Scaffold assembly | 24/02/2025 | 25/03/2025 |
Work Area G | G front - Removal and weathering | 03/03/2025 | 16/04/2025 |
Work Area G | G front - Remediation | 20/05/2025 | 16/06/2025 |
Work Area G | G front - Replacement | 15/07/2025 | 25/08/2025 |
Work Area G | G - Copings | 26/08/2025 | 08/09/2025 |
Work Area H | | | |
Work Area H | H - Scaffold assembly | 17/03/2025 | 25/04/2025 |
Work Area H | H - Removal and weathering | 25/04/2025 | 30/05/2025 |
Work Area H | H - Remediation | 17/06/2025 | 14/07/2025 |
Work Area H | H - Replacement | 15/07/2025 | 01/09/2025 |
Work Area H | H - Copings | 02/09/2025 | 22/09/2025 |
Work Area H | H - Scaffold dismantle | 23/09/2025 | 13/10/2025 |
Work Area I - Steel Panels | | | |
Work Area I - Steel Panels | Penthouse I (first phase) - Steel panel replacement (part) | 08/07/2025 | 15/08/2025 |
Work Area I - Steel Panels | Penthouse I - Structural steel protection design | 29/04/2025 | 12/05/2025 |
Work Area I - Steel Panels | Penthouse I - Structural steel protection install (part 1) | 24/06/2025 | 07/07/2025 |
Work Area I - Steel Panels | Penthouse I - Steel panel leadtime | 13/05/2025 | 23/06/2025 |
Work Area I - Steel Panels | Penthouse I (second phase) - Steel panel replacement | 22/07/2025 | 29/08/2025 |
Work Area I - Steel Panels | Penthouse I - Structural steel protection install (part 2) | 08/07/2025 | 21/07/2025 |