Work Area TitleTaskStart DateEnd Date
A/B Undercroft
A/B Undercroft A/B - Complete25/11/202413/01/2025
Work Area (B)
Work Area (B)B - Complete08/04/202422/08/2024
Work Area (D)
Work Area (D)D - Complete24/06/202413/02/2025
Work Area A
Work Area AA - Complete27/03/202413/09/2024
Work Area C
Work Area C C - Complete22/04/202418/10/2024
Work Area E
Work Area EE - Complete15/07/202413/02/2025
Work Area F
Work Area FF front - Complete28/10/202430/05/2025
Work Area F - Rear
Work Area F - RearF rear - Complete28/10/202415/08/2025
Work Area F - RearF Rear - Scaffold dismantle04/08/202515/08/2025
Work Area G
Work Area GG side - Replacement28/05/202508/07/2025
Work Area GG side - Remediation07/05/202527/05/2025
Work Area GG front - Remediation28/05/202524/06/2025
Work Area GG front - Replacement23/07/202502/09/2025
Work Area GG - Copings03/09/202516/09/2025
Work Area GG - Scaffold dismantle17/09/202510/10/2025
Work Area H
Work Area HH - Removal and weathering25/04/202530/05/2025
Work Area HH - Remediation25/06/202522/07/2025
Work Area HH - Replacement23/07/202509/09/2025
Work Area HH - Copings02/09/202522/09/2025
Work Area HH - Scaffold dismantle23/09/202513/10/2025
Work Area I - Steel Panels
Work Area I - Steel PanelsPenthouse I (first phase) - Steel panel replacement (part 1)16/07/202525/08/2025
Work Area I - Steel PanelsPenthouse I - Structural steel protection design07/05/202520/05/2025
Work Area I - Steel PanelsPenthouse I - Structural steel protection install (part 1)02/07/202515/07/2025
Work Area I - Steel PanelsPenthouse I - Steel panel leadtime21/05/202501/07/2025
Work Area I - Steel PanelsPenthouse I (second phase) - Steel panel replacement22/07/202529/08/2025
Work Area I - Steel PanelsPenthouse I - Structural steel protection install (part 2)08/07/202521/07/2025